Cross the bridge and the rules change. A traffic control plan that satisfies SDOT does not automatically clear Bellevue, Redmond, Kirkland or Issaquah. Each city runs its own permit, its own review clock and its own work-hour windows, and the lead times are further apart than most contractors expect.
If the job sits inside Seattle city limits, start with our guide to SDOT traffic control plan requirements. Everything below applies east of Lake Washington. Every requirement here is drawn from each city’s own current published guidance, linked at the end.
The short version
| City | Permit | Longest lead time published | Work hours |
|---|---|---|---|
| Bellevue | ROW Use Permit (Street Use or Commercial) | 30 days to reserve on-street parking; 14 days for closure dates | Not published as fixed hours |
| Redmond | Right-of-Way Use Permit | 45 days for road closures over 12 hours | Avoid 7-9am and 3-7pm; typically 9am-3pm on arterials |
| Kirkland | ROW permit plus a TTCP under Policy R-29 | Two-week minimum review, per submittal | Not published as fixed hours |
| Issaquah | ROW Permit via MyBuildingPermit.com | Not published; incomplete submittals are not reviewed | 9am-3pm arterials, 8am-4pm busy non-arterials, 7am-6pm residential |
The pattern worth noticing: none of these cities is slow to issue a permit. What catches people out is the notice period attached to the thing they actually want to do – close a lane, reserve parking, shut a street. Redmond’s 45 days for a long closure and Bellevue’s 30 days for reserved parking are the two that most often blow a schedule.
Bellevue
Bellevue works from MUTCD Part VI, the Washington State Modifications (M 24-01), and its own Transportation and Police Department adaptations. Warning signs placed in city right-of-way must be 36 by 36 inches, per MUTCD Table 6F-1 – larger than the default many contractors carry.
- Two-way traffic must be maintained unless an approved temporary traffic control plan authorises otherwise.
- The approved plan has to be kept on site at all times, at 11 by 17 inches minimum.
- Short-duration sidewalk closures need an approved plan that includes pedestrian facilities or a detour, meeting current ADA and PROWAG requirements.
- Closure dates go to the Transportation Inspector a minimum of 14 calendar days ahead, with signs or changeable message signs posted 5 days ahead per the approved plan.
- Temporarily reserving on-street parking is applied for through the ROW permit 30 days in advance.
- Adjacent property and business owners must be notified of scope and schedule at least 48 hours before work starts.
One detail that costs people equipment: a No Parking sign that does not display a permit number is subject to immediate removal, and any traffic control sign lacking an owner’s name and contact number is too. Label everything you put out.
Redmond
Redmond is the most explicit of the four about approval: permits will not be issued unless the Traffic Engineer has approved the traffic control plan. A permit is required for work that disrupts traffic, restricts access or modifies infrastructure in the right-of-way, and separately for any construction use of the right-of-way lasting two weeks or longer.
- Submit the plan as a landscape PDF with the application.
- Road closures longer than 12 hours need a request at least 45 days in advance.
- Temporary no-parking signs go up 48 hours ahead in unrestricted areas, 24 hours ahead where parking is already time-restricted, and must state the date and hours.
- Avoid peak commute periods, generally 7-9am and 3-7pm, unless the Traffic Engineer approves an exception.
- Work within 150 feet of a signalised intersection may require the signal to be placed in flash mode.
Redmond also sets out who has to be present: the person in charge of traffic control or channelisation must hold a certified flagger control card and be on site, or be represented by another knowledgeable certified person, and flaggers need current Washington-recognised certification under WAC 296-155-305.
Standards referenced run deeper than MUTCD alone – WSDOT Standard Plan K drawings, Design Manual M 22-01 chapters 710 and 720, and the Safety Procedures and Guidelines Manual M 75-01.
Kirkland
Kirkland publishes the clearest answer to the question contractors actually ask – when do I need a plan at all? Under Policy R-29, a temporary traffic control plan is required for:
- Work within traffic lanes, shoulders, sidewalks, crosswalks, parking or bicycle facilities on arterial and collector streets
- Work within 200 feet of a signalised intersection
- Work in the Central Business District
- Any project requiring a full or partial road closure
- Special events, public or private, expected to affect city street traffic
- Work on any street Public Works deems necessary
Below those thresholds you still have to implement appropriate traffic control under MUTCD recommendations – the plan requirement goes away, the standard does not.
- Public Works requires a minimum two-week review period for each submittal, so a rejected plan costs another fortnight.
- Plans must be site and project specific. WSDOT and MUTCD sample plans are guidance only and have to be modified; field checks are recommended.
- Road closures should be communicated on portable changeable message signs at least two weeks in advance.
- Temporary No Parking signs must be placed 24 hours before work begins.
- Only one plan may be in use at a time per project; multiple plans must be clearly labelled as separate.
The required contents are specific enough to be worth checking against before you submit: work description, phasing, location, hours and contacts; a vicinity map and legible scaled drawings with a north arrow; posted speed limit and existing channelisation including bus stops, bike lanes, sidewalks and driveways; dimensions for the advance warning, transition, buffer, work and termination areas; device types and sizes in MUTCD designations with spacing; and pedestrian guidance devices.
Issaquah
Issaquah takes applications through MyBuildingPermit.com, and a site-specific traffic control plan is a required component of the plan set. Incomplete submittals are not reviewed at all, and fees are only invoiced once a submittal is deemed sufficient – so a missing plan does not start a clock, it stops one.
- The plan must carry the Traffic Control Supervisor’s contact information and certification number.
- Minimum 10-foot lane widths.
- Work hours are set by road type: 9am-3pm on major arterials, 8am-4pm on busy non-arterials, 7am-6pm on residential roads.
- Devices follow the latest version of the MUTCD; restoration work follows the Issaquah Street Standards (2010).
What all four have in common
Different forms, same four principles:
Planning the equipment
Once the plan is approved, the devices on it have to exist in the right sizes and quantities on the right day. These are the categories Eastside work zones draw on most:
Our Seattle and Marysville yards both serve the Eastside, and the King County service page lists every city we cover. For a closure that needs advance message-sign notice – Kirkland’s two weeks, Bellevue’s five days – book the boards early; they are the item most often short across the region.
Sources
City of Bellevue, Street Use Permit and Right-of-Way Procedures Manual (sections 4.5, 7.4, 10.6) and Appendix D, ROW Use General Conditions.
City of Redmond, Right-of-Way Use Permit and Work Zone Traffic Control Manual.
City of Kirkland, Policy R-29, Temporary Traffic Control Plan Preparation.
City of Issaquah, ROW Permit Submittal Requirements, updated September 2025.
Requirements change. Confirm current rules with the city before you submit.